Critical path method

From CEOpedia | Management online
Revision as of 14:39, 20 March 2022 by Nikshtemenko (talk | contribs)

Critical Path Method or CPM is an important project management technique that helps to schedule and estimate projects. Critical Path Method was developed after World War 2 to schedule and manage complex construction and engineering projects. The method represented a network, where a set of events or activities were connected to each other in a flow manner leading from the beginning to the end. The intention was to represent the sequence of activities and relationships between them. At the same time, another method was developed, which is now closely associated with the CPM - Program evaluation and review technique (PERT). PERT was focusing more on the time that is required to complete an event or activity. As time passed, PERT was largely used together with CPM in project management (Fondahl, J. W., 1987).

Critical Path Method

Critical Path Method is a very powerful tool that provides information on what activities are critical for the project completion, what is the shortest possible project time and how best to schedule work to meet the desired results (Mercier A. G., 1965). Nowadays, many computer programs offer CPM charts based on user characteristics, but the logic of the tool is almost the same for all of them. The project manager lists all tasks that must be completed as part of the project scope, their relationships and time estimates. Each activity or task is given a unique identifier, such as a letter or a number. Each activity is being plotted on the chart in circles and relationships are being established based on the data provided by the project manager. The sequence of relationships is being shown by arrows that are connecting two circles. There is a “start” circle, which links all activities that have no predecessors and there is a “finish” circle for activities that have no successor. A critical path is defined as the longest path in time from start to finish circles. This path indicates the minimum time required to finish the project and all its activities (Levy F. K., Thompson G. L., and Wiest J. D., 1963).

The benefits of using the Critical Path Method are that the project manager can build a clear and cohesive schedule of the project. As part of this schedule, it is possible to see the information about late start and late finish, which also allows the project manager to plan their work and understand the time buffer that is available. Such time buffers can later be used for ad-hoc activities or to prevent the risk of delays (Mercier A. G., 1965).

Modern computerised technologies even allow project managers to apply budget on their critical path chart. This allows the project manager to view at which point in the project which costs will occur. Such information enables project managers to better budget management and mitigates the risks of cash gap or cash deficiency.

The summary of the Critical Path Method

  1. Critical Path Method is a very common technique that is used by many project managers to estimate the duration of the project, dependencies of the tasks and critical activities. CPM is often used together with the Gantt chart in project planning.
  2. Critical Path Method was developed in the late 1950s in the United States for complex construction projects.
  3. Critical Path Method is presented as a chart with a sequence of events from start to finish that represent their dependencies via arrows.
  4. The technology is constantly evolving enabling project managers to apply budget, resources and time estimates on their chart for better coordination and management.

References

  • Fondahl, J. W. (1987). The history of modern project management. Precedence diagramming methods: origins and early development. Project Management Journal, 18(2), 33–36.
  • Levy F. K., Thompson G. L., and Wiest J. D., The ABCs of the Critical Path Method. Harvard Business Review, 1963.
  • Mercier A. G., The Critical Path Method: its fundamentals. Monterey, California: U.S. Naval Postgraduate School, 1965.

Author: Nikita Shtemenko