Life-cycle cost analysis (LCCA)

From CEOpedia

Life-cycle cost analysis (LCCA) is an economic evaluation method that assesses the total cost of owning, operating, maintaining, and disposing of an asset over its entire useful life, enabling comparison of alternatives that may have different initial costs and operational characteristics (NIST 2019, p.7)[1]. The cheapest building to construct may be the most expensive to own. The premium HVAC system that costs 40% more upfront may save 60% on energy over twenty years. A paving material that costs double may last three times as long. LCCA reveals these trade-offs by accounting for all costs through an asset's lifecycle—not just the acquisition price that dominates most purchasing decisions.

The approach matters enormously for infrastructure and capital investments. Initial construction typically represents only 10-15% of a building's total lifecycle cost; operations and maintenance consume the rest. Organizations that minimize purchase price while ignoring future costs make systematically poor decisions. LCCA provides a framework for getting the full picture.

Core principles

LCCA rests on fundamental economic concepts:

Time value of money

Discounting future costs. A dollar spent today costs more than a dollar spent in ten years because today's dollar could be invested and grow. LCCA uses discount rates to convert future costs to present value, enabling fair comparison[2].

Present value calculation. Future costs are discounted by the formula: PV = FV / (1 + r)^n, where r is the discount rate and n is the number of years.

Discount rate selection. Government projects often use rates specified by OMB or agency guidance (historically 3-7% real). Private sector projects use weighted average cost of capital or hurdle rates. The chosen rate significantly affects results.

Analysis period

Study period definition. The analysis must cover an appropriate timeframe—typically the asset's expected useful life or a standard planning horizon (20-40 years for buildings, 20-50 years for infrastructure).

Residual value. Assets with remaining useful life at the analysis period's end retain residual value that offsets costs. Longer-lived alternatives may show better economics partly through higher residual values[3].

Cost categories

LCCA encompasses all ownership costs:

Initial costs

Acquisition costs. Purchase price, construction costs, installation, delivery. These dominate conventional decision-making but represent only a fraction of lifecycle costs.

Design and planning. Engineering, architecture, feasibility studies, environmental review.

Site preparation. Land acquisition, clearing, grading, utilities connection.

Operating costs

Energy. Electricity, gas, fuel consumption over the asset's life. Energy-efficient alternatives may have higher initial costs but lower operating costs.

Water and utilities. Consumption-based utility costs.

Staffing. Personnel required to operate the asset[4].

Consumables. Materials consumed in operation—filters, supplies, chemicals.

Maintenance and repair

Preventive maintenance. Scheduled maintenance to preserve function and extend life.

Corrective maintenance. Repairs responding to failures or deterioration.

Major replacements. Component replacements (roof replacement, HVAC equipment, paving overlays) required during the asset's life.

End-of-life costs

Disposal. Demolition, removal, cleanup, landfill costs.

Decommissioning. Specialized requirements for hazardous materials, environmental remediation.

Salvage value (credit). Recoverable value from resale or recycling offsets disposal costs.

Methodology

Conducting LCCA follows structured steps:

Define alternatives

Comparable function. Alternatives must serve the same basic purpose. Comparing a bridge to a ferry makes sense; comparing a bridge to a building does not.

Technical feasibility. All alternatives must be technically viable for the application[5].

Establish parameters

Analysis period. Select appropriate timeframe aligned with asset life or planning horizon.

Discount rate. Apply appropriate rate for the sector and decision context.

Inflation treatment. Either use constant-dollar analysis (ignoring general inflation) or include inflation consistently across all cost elements.

Estimate costs

Initial costs. Develop cost estimates using standard estimating methods.

Recurring costs. Project annual operating and maintenance costs using historical data, manufacturer specifications, or engineering analysis.

Non-recurring costs. Schedule major repairs and replacements based on expected component lives.

Residual values. Estimate remaining value at analysis period end.

Calculate present values

Discount all costs. Convert each cost stream to present value.

Sum net present costs. Total present value of all costs yields the lifecycle cost[6].

Perform sensitivity analysis

Key assumptions. Test how results change with different discount rates, energy prices, maintenance costs, and useful lives.

Identify decision drivers. Determine which assumptions most affect the conclusion.

Applications

LCCA informs decisions across sectors:

Buildings

HVAC systems. High-efficiency equipment costs more initially but saves energy over time. LCCA reveals the breakeven point and net savings.

Envelope design. Insulation, glazing, and air sealing investments affect construction and energy costs.

Materials selection. Durable materials with longer lives may have lower lifecycle costs despite higher initial prices.

Infrastructure

Pavement design. Thicker initial sections cost more but require less maintenance. LCCA determines optimal design for lowest total cost[7].

Bridge alternatives. Steel versus concrete, different foundation types, rehabilitation versus replacement.

Water and wastewater. Pipeline materials, treatment technologies, pump station configurations.

Equipment procurement

Vehicle fleets. Fuel efficiency, maintenance requirements, and useful life affect total ownership costs.

IT systems. Hardware, software, support, energy, and replacement cycles.

Regulatory and policy context

Requirements often mandate LCCA:

Federal buildings. U.S. federal agencies must conduct LCCA for facility investments under 10 CFR 436.

State requirements. Many states require LCCA for certain public projects.

Rating systems. LEED and other green building systems encourage or require LCCA documentation.

Infrastructure investment. Federal-aid highway projects require LCCA for major pavement investments.

Limitations

LCCA has constraints:

Data uncertainty. Future costs are estimates, not certainties. Energy prices, maintenance needs, and technology changes are difficult to predict accurately.

Discount rate sensitivity. Results depend heavily on discount rate choice. What seems optimal at 3% may not be optimal at 7%[8].

Externalities. Standard LCCA doesn't capture environmental costs, social impacts, or other externalities unless specifically added.

Decision boundaries. LCCA assumes the organization will hold the asset for the full analysis period. If ownership will transfer, incentives may not align.


Life-cycle cost analysis (LCCA)recommended articles
Cost managementInvestment appraisalProject managementAsset management

References

Footnotes

  1. NIST (2019), Life-Cycle Costing Manual, p.7
  2. Fuller S.K., Petersen S.R. (1996), NIST Handbook 135, pp.12-23
  3. FHWA (2017), Life-Cycle Cost Analysis in Pavement Design, pp.8-15
  4. NIST (2019), Life-Cycle Costing Manual, pp.34-45
  5. WBDG (2023), Life-Cycle Cost Analysis
  6. Fuller S.K., Petersen S.R. (1996), NIST Handbook 135, pp.56-78
  7. FHWA (2017), Life-Cycle Cost Analysis in Pavement Design, pp.23-34
  8. NIST (2019), Life-Cycle Costing Manual, pp.67-89

Author: Sławomir Wawak